Trip circuits & lockout relays Startup Checklist
Work scope & measurement context (optional record fields)
References only. This site supplies no acceptance values, test settings, intervals or release instructions. Selecting a scope does not authorize work. Use Remarks for row-specific context; refer to original files, which are not uploaded here.
Draft · technical review pending. Recording prompts only; not procedures or acceptance criteria. Work and access require your approved plan. No normal ranges, pass/fail values, test settings or maintenance intervals are supplied. Condition results are user-entered judgements under separately approved criteria. Evidence/task/measurement OK means the specified record is complete, not healthy equipment. This checklist does not authorize release to service. Unit selection does not convert values.
How to read this form
- As-found observation
- Describe what was observed. OK / Not OK are unavailable.
- Condition
- OK = User assessment under the referenced approved criteria.
- Measurement record
- OK = Required measurement record and context are complete.
- Evidence check
- OK = Required reference or evidence is verified.
- Task record
- OK = The specified recording task is complete.
- Blank / Pending / N/A
- Blank is unclassified. Pending identifies missing checks, evidence or criteria. N/A needs a reason in Remarks.
No row or completed form certifies safety, compliance or fitness for service.
Engineer/date/signature spaces remain for handwriting. Multiple records can be saved locally in this browser and exported; no cloud backup, file attachments or team approval is provided. Older template records stay separate and are not reinterpreted. Keep sensitive information off shared devices.
Compare with an earlier saved inspection
Enter the same Equipment ID, Site and installed-asset identity / serial reference. Only the same template revision is compared. Context and units are shown without conversion or condition verdicts.
Records on hand & preparation
Record the documents and scope available for this inspection. Recording completion is not work authorization.
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 7 | Trip/close coil and control voltage identity are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 8 | Control wiring, terminal and fuse condition are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 9 | Trip circuit supervision and alarm evidence is referencedEvidence check · OK = Required reference or evidence is verified | |||||
| 10 | Approved trip/close operation report identifies source and control modesEvidence check · OK = Required reference or evidence is verified | |||||
| 11 | Approved trip/close circuit functional report — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 12 | Installation/commissioning evidence for trip & close circuits: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 13 | Relay model, serial, firmware and calibration records are retainedEvidence check · OK = Required reference or evidence is verified | |||||
| 14 | Display, LEDs, terminals and auxiliary supply observations are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 15 | Approved settings backup and checksum/revision are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 16 | Injection/functional reports identify functions, binary IO and test equipmentEvidence check · OK = Required reference or evidence is verified | |||||
| 17 | Approved relay-specific injection report — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 18 | Installation/commissioning evidence for relay hardware: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 19 | Approved logic diagram and settings revisions are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 20 | Permissive, trip and alarm test evidence references the tested pathsEvidence check · OK = Required reference or evidence is verified | |||||
| 21 | Temporary overrides and disabled logic are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 22 | Change authorization and as-left configuration evidence are retainedEvidence check · OK = Required reference or evidence is verified | |||||
| 23 | Approved logic/setting verification report — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 24 | Installation/commissioning evidence for logic & settings: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 25 | DC circuit identity, nominal rating and polarity labels are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 26 | Accessible connections, protection and earth fault indications are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 27 | Load and backup source operating records are referencedEvidence check · OK = Required reference or evidence is verified | |||||
| 28 | DC voltage reports identify measurement point and operating conditionEvidence check · OK = Required reference or evidence is verified | |||||
| 29 | Approved DC voltage report — attach the approved report with method, conditions and source reference; only if in scopeMeasurement record · OK = Required measurement record and context are complete | |||||
| 30 | Installation/commissioning evidence for dc circuits: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 31 | Terminal and conductor identity match the reviewed connection drawingEvidence check · OK = Required reference or evidence is verified | |||||
| 32 | Discoloration, insulation damage and heat marks are recorded by terminalEvidence check · OK = Required reference or evidence is verified | |||||
| 33 | Conductor support, bend and strain-relief discrepancies are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 34 | Approved torque/service evidence is referenced without inferring a torque valueEvidence check · OK = Required reference or evidence is verified | |||||
| 35 | Approved connection-resistance report — attach the approved report with method, conditions and source reference; only if in scopeMeasurement record · OK = Required measurement record and context are complete | |||||
| 36 | Installation/commissioning evidence for power connections: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 37 | Corrosion, coating damage and impact marks are recorded by locationEvidence check · OK = Required reference or evidence is verified | |||||
| 38 | Door seals, latches, hinges and covers have documented conditionEvidence check · OK = Required reference or evidence is verified | |||||
| 39 | Water ingress, condensation and contamination evidence are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 40 | Mounting, anchoring and accessible structural supports are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 41 | Enclosure inspection and ingress-control record — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 42 | Installation/commissioning evidence for enclosure & structure: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 43 | Attach original reports, photographs and manufacturer-document referencesTask record · OK = The specified recording task is complete | |||||
| 44 | Record units, method, conditions and instrument identity for each entered resultTask record · OK = The specified recording task is complete | |||||
| 45 | Explain excluded or inapplicable parts and missing evidenceTask record · OK = The specified recording task is complete | |||||
| 46 | Record discrepancies and assign follow-up owner and due-date referenceTask record · OK = The specified recording task is complete | |||||
| 47 | Record qualified review and separately authorized dispositionTask record · OK = The specified recording task is complete | |||||
| 48 | Reference restoration or release records; this checklist does not authorize releaseTask record · OK = The specified recording task is complete |
elecmaint.com · Template V6 · 48 checkpoints · No automatic condition assessment. OK does not certify safety or fitness for service. N/A requires an explanation; unknown/unverified items remain unclassified.