Medium-voltage cables Startup Checklist
Work scope & measurement context (optional record fields)
References only. This site supplies no acceptance values, test settings, intervals or release instructions. Selecting a scope does not authorize work. Use Remarks for row-specific context; refer to original files, which are not uploaded here.
Draft · technical review pending. Recording prompts only; not procedures or acceptance criteria. Work and access require your approved plan. No normal ranges, pass/fail values, test settings or maintenance intervals are supplied. Condition results are user-entered judgements under separately approved criteria. Evidence/task/measurement OK means the specified record is complete, not healthy equipment. This checklist does not authorize release to service. Unit selection does not convert values.
How to read this form
- As-found observation
- Describe what was observed. OK / Not OK are unavailable.
- Condition
- OK = User assessment under the referenced approved criteria.
- Measurement record
- OK = Required measurement record and context are complete.
- Evidence check
- OK = Required reference or evidence is verified.
- Task record
- OK = The specified recording task is complete.
- Blank / Pending / N/A
- Blank is unclassified. Pending identifies missing checks, evidence or criteria. N/A needs a reason in Remarks.
No row or completed form certifies safety, compliance or fitness for service.
Engineer/date/signature spaces remain for handwriting. Multiple records can be saved locally in this browser and exported; no cloud backup, file attachments or team approval is provided. Older template records stay separate and are not reinterpreted. Keep sensitive information off shared devices.
Compare with an earlier saved inspection
Enter the same Equipment ID, Site and installed-asset identity / serial reference. Only the same template revision is compared. Context and units are shown without conversion or condition verdicts.
Records on hand & preparation
Record the documents and scope available for this inspection. Recording completion is not work authorization.
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 7 | Cable ID, construction, route and termination points are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 8 | Accessible jacket damage, deformation and heat marks are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 9 | Bending, support and environmental exposure discrepancies are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 10 | Diagnostic report identifies cable length, connected assets and methodEvidence check · OK = Required reference or evidence is verified | |||||
| 11 | Insulation resistance from an approved cable test report, if included in scope; retain method, applied voltage, duration and test conditionsMeasurement record · OK = Required measurement record and context are complete | |||||
| 12 | Approved cable-specific insulation or diagnostic report; retain method — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 13 | Installation/commissioning evidence for cable body: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 14 | Termination/joint type and installation reference are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 15 | Stress-control surfaces, insulation and seals are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 16 | Cable gland, strain relief and phase identification condition are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 17 | Joint heating, moisture ingress and installation/test evidence are referencedEvidence check · OK = Required reference or evidence is verified | |||||
| 18 | Termination/splice installation and approved verification report — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 19 | Installation/commissioning evidence for terminations & joints: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 20 | Shield/sheath and bonding scheme are identified from reviewed drawingsEvidence check · OK = Required reference or evidence is verified | |||||
| 21 | Accessible bonds, link boxes and sheath condition are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 22 | Link box seals, SVLs and identification are recorded where fittedEvidence check · OK = Required reference or evidence is verified | |||||
| 23 | Sheath test and bonding verification reports identify sections and connectionsEvidence check · OK = Required reference or evidence is verified | |||||
| 24 | Approved sheath/bonding verification report — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 25 | Installation/commissioning evidence for cable shields: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 26 | Tray/support type, loading reference and route are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 27 | Corrosion, loose attachments and displaced supports are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 28 | Sharp edges, cable abrasion and congestion observations are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 29 | Support modifications and bonding/fire-barrier interfaces are referencedEvidence check · OK = Required reference or evidence is verified | |||||
| 30 | Cable-support inspection and installation reference — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 31 | Installation/commissioning evidence for supports & trays: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 32 | Penetration ID and listed/approved firestop system reference are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 33 | Seal condition, gaps and unauthorized penetrations are documentedEvidence check · OK = Required reference or evidence is verified | |||||
| 34 | Labels and substrate/service changes are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 35 | Qualified repair/inspection evidence identifies the actual systemEvidence check · OK = Required reference or evidence is verified | |||||
| 36 | Firestop system inspection record and approved installation reference — attach the approved report with method, conditions and source reference; only if in scopeEvidence check · OK = Required reference or evidence is verified | |||||
| 37 | Installation/commissioning evidence for fire barriers: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 38 | Protective earth and bonding conductor identification is recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 39 | Accessible bonds, clamps and joints show documented conditionEvidence check · OK = Required reference or evidence is verified | |||||
| 40 | Missing conductors, corrosion and mechanical damage are recordedEvidence check · OK = Required reference or evidence is verified | |||||
| 41 | Reviewed earth drawing and continuity measurement locations are referencedEvidence check · OK = Required reference or evidence is verified | |||||
| 42 | Approved bonding-continuity report — attach the approved report with method, conditions and source reference; only if in scopeMeasurement record · OK = Required measurement record and context are complete | |||||
| 43 | Installation/commissioning evidence for grounding & bonding: drawing/manual revision, as-installed configuration and unresolved punch-list referenceEvidence check · OK = Required reference or evidence is verified |
| No. | Checkpoint | Value / observation | OK | Not OK | N/A | Remarks |
|---|---|---|---|---|---|---|
| 44 | Attach original reports, photographs and manufacturer-document referencesTask record · OK = The specified recording task is complete | |||||
| 45 | Record units, method, conditions and instrument identity for each entered resultTask record · OK = The specified recording task is complete | |||||
| 46 | Explain excluded or inapplicable parts and missing evidenceTask record · OK = The specified recording task is complete | |||||
| 47 | Record discrepancies and assign follow-up owner and due-date referenceTask record · OK = The specified recording task is complete | |||||
| 48 | Record qualified review and separately authorized dispositionTask record · OK = The specified recording task is complete | |||||
| 49 | Reference restoration or release records; this checklist does not authorize releaseTask record · OK = The specified recording task is complete |
elecmaint.com · Template V6 · 49 checkpoints · No automatic condition assessment. OK does not certify safety or fitness for service. N/A requires an explanation; unknown/unverified items remain unclassified.